Construction Phases

Phase Two

  • Began January 7, 2013
  • Submitted construction drawings to the Department of Permitting Services
  • Building permit to be issued
  • Planned to last 22 months, followed by 8-12 week period to close Colesville Rd. library and set up new library building

Phase One

  • Completed utility relocation work:
  • Relocated both the storm and sanitary sewers
  • Built conduit under the roadway for the “dry utilities to relocated their cables from the telephone poles along Wayne Ave. (Pepco, Verizon, and Comcast have finished relocating their cables)
  • Repaved Fenton St.
  • Reinstalled parking meters along Bonifant St.
Please do not walk or drive onto the grounds, even if the construction gate is open. Keep Out signs have been posted. For safety and security reasons, the construction manager will ask anyone entering the site to leave.

1 comment:

  1. This individual discovered his very first beet fields inside Malaysia two decades previously, discovered prosperous factories perched in close proximity to areas, factories in which chosen employees, purchased provides along with settled income tax for you to local governments along with usually triggered a new rising hold involving continual affluence by which zero homeowner right or indirectly had been denied enable you to drop into your treasure-trove produced out of beet fields. construction companies san francisco