During this period Costello Construction Company:
- Began vapor barrier application at the north elevation and along X-1 line.
- Rough in west side exterior walls electric and data; boxes and conduit complete through 5th floor.
- Installed duct hangers at the 3rd and 4th floor ceilings.
- Installed plumbing overhead pipe at the 3rd floor.
- Completed installing the roof deck and shear studs west and east of X-1 line.
- Completed 4th floor steel decking.
- Poured the ramp at the main entry.
- Completed cutting-in added vertical control joints at 2nd floor CMU walls.
- Core drilled for waste and vent pipe at the 3rd and 4th floors.
- Completed cutting the concrete floor west side of the elevator shaft for electrical risers.
- Plumbing rough-in at the basement is 85% complete.
- Duct installation at the lower level is 95% complete.
- Completed stone veneer installation at the north elevation.
- Started stone veneer installation 1st floor vicinity.
- Framed metal studs for soffits west side.
- Completed exterior stud wall framing and sheathing west side.
- Completed erecting hanging steel N.E. corner sequence 15-19.
Labels: Silver Spring