During this period Costello Construction Company:
- Completed vapor barrier application at the north elevation and along X-1 line.
- Began installing window washing fixtures at the roof.
- Installed beams added for window washing equipment
- Began vapor barrier application at the south elevation 1st floor and along west side of pavilion.
- Completed radiant heat piping installation at the 5th floor.
- Completed Pavilion roof steel decking.
- Began roof drain installation
- Completed cutting the concrete floor level 5 along the approved construction joint and added reinforced steel.
- Installed electrical floor box sleeves at floors 3,4 and 5.
- Completed sprinkler pipe rough-in at the 1st and 2nd floors.
- Installed duct riser and smoke exhaust fan sleeve at the roof.
- Completed stone veneer installation 1st and 2nd floor vicinity.
- Electrical rough-in and install panel board boxes at the Electrical room.
Prepared by F. Ware
Labels: Silver Spring