Tuesday, February 25, 2014

Construction Update: November 12, 2013- November 26, 2013

During this period Costello Construction Company:


  • Electricians installed temporary power and lighting to upper floors.
  • Electricians installed conduit racks and back boxes at the electric room.
  • Completed decking and shear studs at floors 4 and 5 west of X-1 line.
  • Delivered and began installing the roof deck west of X-1 line.
  • Placed and finished concrete composite slab 4th and 5th floor west of X-1 line.
  • Delivered and installed cantilever truss at line 2.
  • Core drilled and installed waste and vent pipe at the 1st and 2nd floor. 
  • Began below grade duct at the pavilion.
  • Installed steel stud exterior framing , west side at the 2nd and 3rd floor.
  • Installed spray fire proofing at the 3rd floor west of X-1 line. 
  • Completed CMU walls at the 4th floor; north elevation.
  • Electrical rough-in and install panel board boxes at the Electrical Room. 
  • Mobilized the fire protection contractor and began riser rough-in at the basement . 
  • Delivered and erected Masons scaffold system at the north and south elevation.
  • Installed stair #2  from the 1st floor to the 5th floor.
  • Delivered steel sequence 16 and 17 and began installation. 

Prepared by F. Ware 

Construction Update: January 28, 2014- February 18, 2014

During this period Costello Construction Company:


  • Completed vapor barrier application at the north elevation and along X-1 line. 
  • Began installing window washing fixtures at the roof.
  • Installed beams added for window washing equipment 
  • Began vapor barrier application at the south elevation 1st floor and along west side of pavilion.
  • Completed radiant heat piping installation at the 5th floor.
  • Completed Pavilion roof steel decking.
  • Began roof drain installation 
  • Completed cutting the concrete floor level 5 along the approved construction joint and added reinforced steel.  
  • Installed electrical floor box sleeves at floors 3,4 and 5. 
  • Completed sprinkler pipe rough-in at the 1st and 2nd floors.
  • Installed duct riser and smoke exhaust fan sleeve at the roof.
  • Completed stone veneer installation 1st and 2nd floor vicinity. 
  • Electrical rough-in and install panel board boxes at the Electrical room.

Prepared by F. Ware 

Construction Update: January 7, 2014- January 28, 2014


During this period Costello Construction Company:


  • Began vapor barrier application at the north elevation and along X-1 line.
  • Rough in west side exterior walls electric and data; boxes and conduit complete through 5th floor. 
  • Installed duct hangers at the 3rd and 4th floor ceilings.
  • Installed plumbing overhead pipe at the 3rd floor. 
  • Completed installing the roof deck and shear studs west and east of X-1 line. 
  • Completed 4th floor steel decking.
  • Poured the ramp at the main entry.
  • Completed cutting-in added vertical control joints at 2nd floor CMU walls. 
  • Core drilled for waste and vent pipe at the 3rd and 4th floors. 
  • Completed cutting the concrete floor west side of the elevator shaft for electrical risers. 
  • Plumbing rough-in at the basement is 85% complete. 
  • Duct installation at the lower level is 95% complete.
  • Completed stone veneer installation at the north elevation. 
  • Started stone veneer installation 1st floor vicinity.
  • Framed metal studs for soffits west side. 
  • Completed exterior stud wall framing and sheathing west side. 
  • Completed erecting hanging steel N.E.  corner sequence 15-19.