During this period Costello Construction Company:
- Stripped remaining forms at core walls
- Installed waterproofing , drain tiles and controlled fill at the east side X-1 line and the south side of stair #1
- Continued waterproofing and compacted fill against foundation walls at the west side
- Poured grade beam footing at x-1 line vicinity of column line #3
- Formed and poured the foundation wall; same area
- Prep and pour the remaining basement slab on grade
- Formed and poured 2 concrete encased columns
- Formed and poured the dumpster enclosure walls to the 2nd floor
- Installed metal door frames and masonry walls at the lower level
- Installed masonry walls at the upper level north east corner
- Completed second floor decking , poured stops and shear studs
- Began steel erection at the pavilion
- Erected steel to the 3rd floor and began decking
- started steel erection to the 4th floor.
Prepared by F. Ware
Labels: Silver Spring