During this period Costello Construction Company:

  • Completed the mud mat, below slab waterproofing and vapor barrier at the lower level 
  • Installed the trench drain at the lower level
  • Completed prep. and concrete placement at the lower level slab on grade
  • Poured the 12 inch concrete curb at the lower level
  • Re-mobilized the Steel Erectors to complete the remainder of the structural steel
  • Continued waterproofing and compacted fill against foundation walls at the west side
  • Removed climbing forms elevator 2 and 3
  • Completed 5th floor foundation walls vicinity elevator 1 lobby
  • Completed concrete core walls at elevator 1, stair 1 from the 5th floor to the roof
  • Removed climbing forms stair 1/ elevator 1
  • Formed and poured core walls at elevator 4 and 5 from the 4th floor to the roof
  • Erected steel to the 3rd floor and began decking
  • Started steel erection to the 4th floor. 


Prepared by F. Ware