Construction Update: October 30, 2013 - November 12, 2013


During this period Costello Construction Company: 
  • Installed roof trusses at Column line 2 and 1, sequence 11 and 13
  • Installed connecting steel sequence 11 and 12
  • Mobilized a 2nd crane for truss erection
  • Installed roof and 4th floor decking at the Pavilion sequence 9
  • Installed decking at the 5th floor west of X-1 line sequence 8
  • Core drilled for storm pipe at the 2nd floor and 3rd floor
  • Applied spray fire proofing at the 2nd floor and started the 3rd floor
  • Mobilized the Drywall Contractor and completed layout at the 2nd and 3rd floor 
  • Stocked steel studs for exterior walls at the 1st three floors
  • Completed CMU walls at the 3rd floor; north elevation
  • Electrical rough in and installed panel board boxes at the Electrical Room
  • Completed steel erection to the 5th floor west of X-1 line sequence 8 and 11
  • Began overhead storm pipe rough in at the 1st floor ceiling space 
  • Installed stair #2 from the basement to 1st floor
  • Delivered steel sequence 11, 13 and 18 
  • Poured the pad for sample wall. 
Prepared by F. Ware 