Construction Update: August 7 to August 20, 2013

During this period Costello Construction Company:


  • Completed plumbing below slab rough-in at the lower level;
  • Completed plumbing slab rough-in at the Pavilion; 
  • Located existing sanitary pipe and made tie in;
  • Installed waterproofing, drain tile and gravel and compacted fill against the foundation wall , north and west side;
  • Located existing water line;
  • Completed concrete core walls from the 4th floor to the roof at elevator 2 and 3;
  • Completed 2nd to 3rd floor foundation walls vicinity elevator 1 lobby;
  • Completed concrete core walls at elevator 1, stair 1 from the 4th floor to the 5th floor;
  •  Completed electrical rough-in at the lower level sub grade;
  • Started forming foundation walls at the dumpster enclosure to the 1st floor. 

Prepared by F. Ware 