Construction Update: July 23 to August 6, 2013

During this period Costello Construction Company:


  • Continued plumbing rough-in at the lower level ( 95% complete);
  • Completed back fill and compaction at the Pavilion interior walls;
  • Began steel columns and beams at the 2nd floor;
  • Installed waterproofing and compacted fill against foundation walls east side;
  • Installed waterproofing , drain tile and gravel fill against the foundation wall, north and west side;
  • Received MEVA forms for elevator 4/5 core walls;
  • Completed 1st floor to 2nd floor foundation walls vicinity elevator 1 lobby;
  • Completed concrete core walls at elevator 1, stair 1 from the 3rd to 4th floor;
  • Began installation of 2nd floor steel decking;
  • Placed and finished 1st floor concrete slab on deck to column line 3;
  • Began electrical rough-in at the lower level sub grade. 

Prepared by F. Ware