During this period Costello Construction Company:
- Continued plumbing rough-in at the Pavilion and lower level;
- Began back fill and compaction at the Pavilion;
- Installed steel columns and beams through the 2nd floor to line 3;
- Finalized action plan for concrete wall honeycomb repairs;
- Completed foundation wall concrete at the basement with the exception of the access opening;
- Completed 1st floor to 2nd floor foundation walls vicinity elevator 1 lobby;
- Completed concrete core walls at elevator 1, stair 1 from 1st to 2nd floor;
- Installed 1st floor steel decking including shear studs and Inspection;
- Began wire mesh , reinforced steel and forms at the 1st floor elevated deck.
Prepared by F. Ware
Labels: Silver Spring