Tuesday, August 20, 2013

Construction Update : July 10 to July 23, 2013


During this period Costello Construction Company:

  • Continued plumbing rough-in at the Pavilion and lower level; 
  • Began back fill and compaction at the Pavilion;
  • Installed steel columns and beams through the 2nd floor to line 3; 
  • Finalized action plan for concrete wall honeycomb repairs; 
  • Completed foundation wall concrete at the basement with the exception of the access opening;
  • Completed 1st floor to 2nd floor foundation walls vicinity elevator 1 lobby;
  • Completed concrete core walls at elevator 1, stair 1 from 1st to 2nd floor; 
  •  Installed 1st floor steel decking including shear studs and Inspection;
  • Began wire mesh , reinforced steel and forms at the 1st floor elevated deck. 

Prepared by F. Ware 

Construction Update: August 7 to August 20, 2013

During this period Costello Construction Company:


  • Completed plumbing below slab rough-in at the lower level;
  • Completed plumbing slab rough-in at the Pavilion; 
  • Located existing sanitary pipe and made tie in;
  • Installed waterproofing, drain tile and gravel and compacted fill against the foundation wall , north and west side;
  • Located existing water line;
  • Completed concrete core walls from the 4th floor to the roof at elevator 2 and 3;
  • Completed 2nd to 3rd floor foundation walls vicinity elevator 1 lobby;
  • Completed concrete core walls at elevator 1, stair 1 from the 4th floor to the 5th floor;
  •  Completed electrical rough-in at the lower level sub grade;
  • Started forming foundation walls at the dumpster enclosure to the 1st floor. 

Prepared by F. Ware 

Construction Update: July 23 to August 6, 2013

During this period Costello Construction Company:


  • Continued plumbing rough-in at the lower level ( 95% complete);
  • Completed back fill and compaction at the Pavilion interior walls;
  • Began steel columns and beams at the 2nd floor;
  • Installed waterproofing and compacted fill against foundation walls east side;
  • Installed waterproofing , drain tile and gravel fill against the foundation wall, north and west side;
  • Received MEVA forms for elevator 4/5 core walls;
  • Completed 1st floor to 2nd floor foundation walls vicinity elevator 1 lobby;
  • Completed concrete core walls at elevator 1, stair 1 from the 3rd to 4th floor;
  • Began installation of 2nd floor steel decking;
  • Placed and finished 1st floor concrete slab on deck to column line 3;
  • Began electrical rough-in at the lower level sub grade. 

Prepared by F. Ware