Construction Update: June 26, 2013 to July 9, 2013

During this period Costello Construction Company:


  • Began erecting steel for first floor of building on July 2, 2013;
  • Received cast iron soil pipe and began plumbing rough in at the pavilion and lower level;
  • Installed drain tile system at the pavilion interior areas;
  • Installed rebar, formwork and pour concrete foundation walls at elevators 1 and stair 1 to the first floor;
  • Installed formwork, reinforcing steel and concrete placement from lower level to first floor at elevators 2 and 3 ;
  • Continued rebar placement and concrete placement at basement foundation walls.
  • Completed backfill, re-grading and compaction work is underway at the basement to re-establish grade;
  • Completed as-built survey of remaining caissons;
  • Completed masonry wall grouting at the pavilion;
  • Installed concrete base and fiberglass sump tank vicinity of the loading dock. 

Prepared by Fran Ware 