During this period Costello Construction Company:
- Mobilized the crane for concrete construction;
- Waterproofed concrete walls at the Pavilion and escalator pit;
- Continued rebar placement at basement foundation walls;
- Completed waterproofing at elevators 1, 2, and 3 and stair 1 foundation walls;
- Placed concrete for basement foundation walls; 3 pours completed to date;
- Completed partial back fill of foundation walls including drain tiles;
- Installed Masonry foundation walls at the Pavilion;
- Installed rebar, formwork and poured concrete foundation walls at elevators 1 and stair 2.
Prepared by Fran Ware