During this period Costello Construction Company:
- Completed grade beams and footers;
- Completed waterproofing elevators at 1, 2 &3;
- Installed sleeves for the elevator pits;
- Finished elevator pits;
- Completed all piers in the Pavilion.
Prepared by Fran Ware