Construction Update: May 15, 2013 to May 28, 2013

During this period Costello Construction Company:
  • Completed grade beams and footers;
  • Completed waterproofing elevators at 1, 2 &3;
  • Installed sleeves for the elevator pits;
  • Finished elevator pits;
  • Completed all piers in the Pavilion.
Prepared by Fran Ware