Construction Update: April 30, 2013 to May 14, 2013

During this period Costello Construction Company:
  • Completed reinforcing steel at Mat B;
  • Completed placing concrete at Mat B;
  • Began rebar replacement at basement foundation walls;
  • Excavated and placed rebar and concrete for wall footings, north end of basement;
  • Placed concrete for remaining grade beams at the basement;
  • Installed meter and temporary power to the trailer compound;
  • Install rebar and pour concrete foundation walls at elevators 2 and 3;
  • Continue as-built surveys of caissons with two remaining.
Prepared by Fran Ware 