Tuesday, June 11, 2013

Construction Update: May 29, 2013 to June 11, 2013

 During this period Costello Construction Company:
  • Mobilized the crane for concrete construction;
  • Waterproofed concrete walls at the Pavilion and escalator pit;
  • Continued rebar placement at basement foundation walls;
  • Completed waterproofing at elevators 1, 2, and 3 and stair 1 foundation walls;
  • Placed concrete for basement foundation walls; 3 pours completed to date;
  • Completed partial back fill of foundation walls including drain tiles;
  • Installed Masonry foundation walls at the Pavilion;
  • Installed rebar, formwork and poured concrete foundation walls at elevators 1 and stair 2.


Prepared by Fran Ware 

Monday, June 3, 2013

Construction Update: May 15, 2013 to May 28, 2013

During this period Costello Construction Company:
  • Completed grade beams and footers;
  • Completed waterproofing elevators at 1, 2 &3;
  • Installed sleeves for the elevator pits;
  • Finished elevator pits;
  • Completed all piers in the Pavilion.
Prepared by Fran Ware

Construction Update: April 30, 2013 to May 14, 2013

During this period Costello Construction Company:
  • Completed reinforcing steel at Mat B;
  • Completed placing concrete at Mat B;
  • Began rebar replacement at basement foundation walls;
  • Excavated and placed rebar and concrete for wall footings, north end of basement;
  • Placed concrete for remaining grade beams at the basement;
  • Installed meter and temporary power to the trailer compound;
  • Install rebar and pour concrete foundation walls at elevators 2 and 3;
  • Continue as-built surveys of caissons with two remaining.
Prepared by Fran Ware