Construction Update: April 16, 2013 to April 30, 2013

During this period Costello Construction Company:


  • Completed reinforcing steel at Mat A;
  • Completed placing concrete at Mat A;
  • Completed placing concrete and reinforcing steel at Mat C;
  • Completed caisson construction : all caissons poured, fabricated and tested; 
  • Placed concrete for grade beams at the pavilion;
  • Completed excavating Mat B with mud mat, at the basement;
  • Pepco has energized temporary power for the trailer compound;
  • As-built survey of caissons continues;
  • CSL testing at caissons continues;
  • Installation of rebar and concrete foundation walls at elevator 4 and 5. 

Prepared by Fran Ware 