Construction Update: March 20 to April 2, 2013

During this period Costello Construction Company:

Continued building caisson rebar cages; 
Completed partial layout for test borings in basement and remainder of pavilion; 
Continued test borings in basement and completed at the pavilion; 
Completed installation of excavation support system;
Completed drilling and installing 30 caissons;
Performed CSL testing of Caissons CS 17, 18, 19, 20, 21, and 3E; 
Continued to stockpile excavated soil. 

Prepared by Fran Ware 