Construction Update: April 2 to April 16, 2013

During this period Costello Construction Company:
  • Completed building caissons rebar cages;
  • Completed test borings in basement and remainder of Pavilion;
  • Reinforced steel and concrete placement completed at mat C;
  • Drilled and installed 41 completed caissons;
  • Excavated and placed reinforcing steel for grade beams at the Pavilion;
  • Began excavating mat A at the basement;
  • Prepared foundation layout at the Pavilion;
  • Performed as-built survey of caissons at the Pavilion.