Saturday, April 20, 2013

Construction Update: April 2 to April 16, 2013

During this period Costello Construction Company:
  • Completed building caissons rebar cages;
  • Completed test borings in basement and remainder of Pavilion;
  • Reinforced steel and concrete placement completed at mat C;
  • Drilled and installed 41 completed caissons;
  • Excavated and placed reinforcing steel for grade beams at the Pavilion;
  • Began excavating mat A at the basement;
  • Prepared foundation layout at the Pavilion;
  • Performed as-built survey of caissons at the Pavilion.

Prepared by Fran Ware 



 


Tuesday, April 9, 2013

Construction Update: March 20 to April 2, 2013

During this period Costello Construction Company:

Continued building caisson rebar cages; 
Completed partial layout for test borings in basement and remainder of pavilion; 
Continued test borings in basement and completed at the pavilion; 
Completed installation of excavation support system;
Completed drilling and installing 30 caissons;
Performed CSL testing of Caissons CS 17, 18, 19, 20, 21, and 3E; 
Continued to stockpile excavated soil. 

Prepared by Fran Ware