Construction Update: November 12, 2013- November 26, 2013

During this period Costello Construction Company:


  • Electricians installed temporary power and lighting to upper floors.
  • Electricians installed conduit racks and back boxes at the electric room.
  • Completed decking and shear studs at floors 4 and 5 west of X-1 line.
  • Delivered and began installing the roof deck west of X-1 line.
  • Placed and finished concrete composite slab 4th and 5th floor west of X-1 line.
  • Delivered and installed cantilever truss at line 2.
  • Core drilled and installed waste and vent pipe at the 1st and 2nd floor. 
  • Began below grade duct at the pavilion.
  • Installed steel stud exterior framing , west side at the 2nd and 3rd floor.
  • Installed spray fire proofing at the 3rd floor west of X-1 line. 
  • Completed CMU walls at the 4th floor; north elevation.
  • Electrical rough-in and install panel board boxes at the Electrical Room. 
  • Mobilized the fire protection contractor and began riser rough-in at the basement . 
  • Delivered and erected Masons scaffold system at the north and south elevation.
  • Installed stair #2  from the 1st floor to the 5th floor.
  • Delivered steel sequence 16 and 17 and began installation. 

Prepared by F. Ware 