Construction Update: January 28, 2014- February 18, 2014

During this period Costello Construction Company:


  • Completed vapor barrier application at the north elevation and along X-1 line. 
  • Began installing window washing fixtures at the roof.
  • Installed beams added for window washing equipment 
  • Began vapor barrier application at the south elevation 1st floor and along west side of pavilion.
  • Completed radiant heat piping installation at the 5th floor.
  • Completed Pavilion roof steel decking.
  • Began roof drain installation 
  • Completed cutting the concrete floor level 5 along the approved construction joint and added reinforced steel.  
  • Installed electrical floor box sleeves at floors 3,4 and 5. 
  • Completed sprinkler pipe rough-in at the 1st and 2nd floors.
  • Installed duct riser and smoke exhaust fan sleeve at the roof.
  • Completed stone veneer installation 1st and 2nd floor vicinity. 
  • Electrical rough-in and install panel board boxes at the Electrical room.

Prepared by F. Ware 