Wednesday, March 20, 2013

Construction Update: March 6 to March 19, 2013

Posted by Fran Ware 
Silver Spring site March 5
During this period Costello Construction Company:
  • Continued building caisson rebar cages;
  • Performed partial layout for test borings in basement and remainder of pavilion;
  • Continued installation of excavating support system; 
  • Installed balance of caissons at the pavilion;
  • Continued test borings in basement and completed at the pavilion;
  • Relocated temporary power shed; 
  • Performed CSL testing of Caissons CS 17, 18, 19, 20, 21 and 3E; 
  • Installed fabric panels on construction fence;
  • Installed 2nd construction fence. 

Monday, March 4, 2013

Construction Update: February 6 to March 5, 2013

Posted by Fran Ware
During this period Costello Construction Company:
  • Completed test borings at mat "C";
  • Continued building caisson rebar cages;
  • Prepared layout for caissons at mat "C";
  • Received four loads of foundation rebar;
  • Performed CSL testing of test caisson;
  • Completed installing gear in electric shed.