Construction Update: October 15, 2013- October 29, 2013


During this period Costello Construction Company :
  • Installed roof trusses at column line 3 and 4 sequence 8
  • formed and poured the concrete wall to the 3rd floor vicinity of column line #1
  • Installed 4th floor decking at the pavilion sequence 7
  • Applied spray fire proofing at the 1st floor and started the 2nd floor 
  • Prep and poured concrete at 3rd floor composition deck west of X-1 line
  • Completed CMU walls at the 2nd floor; north elevation 
  • Electrical rough in at masonry walls
  • Erected steel from sequence 8 to 10
  • Completed steel erection to the 4th floor west of X-1 line
  • Began overhead duct and storm pipe rough in at the lower level  
  • Installed MEP hangers prior to fireproofing at the 1st floor
  • Delivered steel sequence 11 and 12
  • Formed and poured concrete walls from 1st and 2nd floor vicinity of the loading dock. 

Prepared by F. Ware 