Construction Update: February 6 to March 5, 2013

Posted by Fran Ware
During this period Costello Construction Company:
  • Completed test borings at mat "C";
  • Continued building caisson rebar cages;
  • Prepared layout for caissons at mat "C";
  • Received four loads of foundation rebar;
  • Performed CSL testing of test caisson;
  • Completed installing gear in electric shed.