Monday, January 21, 2013

Construction Update: January 7 to January 22, 2013

Posted by Fran Ware
Notice to proceed with the project issued to Costello Construction by Montgomery County on January 7, 2013.
During this period, Costello Construction Company:
  • Received notice to proceed;
  • Began mobilization with trailers & earth moving equipment;
  • Received erosion /sediment controls and foundation permits;
  • Held a Site preconstruction meeting; 
  • Installed the construction fence;
  • Held a preparatory meeting for E & S installation;
  • Installed super silt fence for E & S perimeter controls; 
  • Began clearing and grubbing; and
  • Continued with submittals.