Monday, May 6, 2013

Construction Update: April 16, 2013 to April 30, 2013

During this period Costello Construction Company:


  • Completed reinforcing steel at Mat A;
  • Completed placing concrete at Mat A;
  • Completed placing concrete and reinforcing steel at Mat C;
  • Completed caisson construction : all caissons poured, fabricated and tested; 
  • Placed concrete for grade beams at the pavilion;
  • Completed excavating Mat B with mud mat, at the basement;
  • Pepco has energized temporary power for the trailer compound;
  • As-built survey of caissons continues;
  • CSL testing at caissons continues;
  • Installation of rebar and concrete foundation walls at elevator 4 and 5. 

Prepared by Fran Ware 

Saturday, April 20, 2013

Construction Update: April 2 to April 16, 2013

During this period Costello Construction Company:
  • Completed building caissons rebar cages;
  • Completed test borings in basement and remainder of Pavilion;
  • Reinforced steel and concrete placement completed at mat C;
  • Drilled and installed 41 completed caissons;
  • Excavated and placed reinforcing steel for grade beams at the Pavilion;
  • Began excavating mat A at the basement;
  • Prepared foundation layout at the Pavilion;
  • Performed as-built survey of caissons at the Pavilion.

Prepared by Fran Ware 



 


Tuesday, April 9, 2013

Construction Update: March 20 to April 2, 2013

During this period Costello Construction Company:

Continued building caisson rebar cages; 
Completed partial layout for test borings in basement and remainder of pavilion; 
Continued test borings in basement and completed at the pavilion; 
Completed installation of excavation support system;
Completed drilling and installing 30 caissons;
Performed CSL testing of Caissons CS 17, 18, 19, 20, 21, and 3E; 
Continued to stockpile excavated soil. 

Prepared by Fran Ware 


Wednesday, March 20, 2013

Construction Update: March 6 to March 19, 2013

Posted by Fran Ware 
Silver Spring site March 5
During this period Costello Construction Company:
  • Continued building caisson rebar cages;
  • Performed partial layout for test borings in basement and remainder of pavilion;
  • Continued installation of excavating support system; 
  • Installed balance of caissons at the pavilion;
  • Continued test borings in basement and completed at the pavilion;
  • Relocated temporary power shed; 
  • Performed CSL testing of Caissons CS 17, 18, 19, 20, 21 and 3E; 
  • Installed fabric panels on construction fence;
  • Installed 2nd construction fence. 

Monday, March 4, 2013

Construction Update: February 6 to March 5, 2013

Posted by Fran Ware
During this period Costello Construction Company:
  • Completed test borings at mat "C";
  • Continued building caisson rebar cages;
  • Prepared layout for caissons at mat "C";
  • Received four loads of foundation rebar;
  • Performed CSL testing of test caisson;
  • Completed installing gear in electric shed.

Wednesday, February 13, 2013

Construction Update: January 23 to February 5, 2013

Posted by Fran Ware

During this period, Costello Construction Company:

  • Completed the trailer set up;
  • Excavated pad to 8';
  • Began testing borings;
  • Began fabrication of rebar cages for caissons;
  • Competed construction fence at Wayne Ave; and
  • Erected the temporary power shed.

Monday, January 21, 2013

Construction Update: January 7 to January 22, 2013

Posted by Fran Ware
Notice to proceed with the project issued to Costello Construction by Montgomery County on January 7, 2013.
During this period, Costello Construction Company:
  • Received notice to proceed;
  • Began mobilization with trailers & earth moving equipment;
  • Received erosion /sediment controls and foundation permits;
  • Held a Site preconstruction meeting; 
  • Installed the construction fence;
  • Held a preparatory meeting for E & S installation;
  • Installed super silt fence for E & S perimeter controls; 
  • Began clearing and grubbing; and
  • Continued with submittals.